Waterloo Memorial Recreation Complex Expansion

The Waterloo Memorial Recreation Complex expansion is underway. Find the latest construction updates below.


On this page

  1. Project background
  2. Construction updates
  3. Impacts to local residents
  4. Construction timelines

Project background

This project supports the vision of the recreation and leisure services master plan approved by council in November 2008, which recognizes a demand for new facility space as the city’s population continues to grow and new trends in recreation activities emerge.

We are building:

  • a new civic front on the east side of the building that will include an activity court/gymnasium, additional lobby space, change rooms, inclusive washrooms
  • a renovated Hauser Haus to allow for additional fitness programming in two exercise studios and a secondary indoor walking concourse
  • a new two-storey building - the Community Pavilion - on the west-side of the property as the new home for the city’s older adult recreation program currently offered at the Adult Recreation Centre (ARC) and Wing 404 RCAFA Rotary Adult Centre. The building will connect to the WMRC facility with an elevated pedestrian bridge

Construction updates

On January 11, 2021, the Province of Ontario issued a provincial declaration of emergency and stay at home order. Municipal projects are exempt from this order, therefore the Waterloo Memorial Recreation Complex expansion project will continue as planned.

On April 16, 2021, the Province of Ontario issued a second emergency stay at home order. Municipal projects are exempt from this order, therefore this expansion project will continued as planned.

The following construction activity is underway:

Community Pavilion:

  • interior masonry is completed
  • much of the first floor drywall is installed and we have started on the drywall on the second floor
  • interior mechanical electrical infrastructure is 80% complete
  • elevator is currently being installed
  • plumbing is substantially completed with many of the fixtures installed
  • almost all of the glazing is installed with much of the exterior block work completed

Civic Front:

  • almost all of the mechanical and electrical infrastructure has been installed.
  • most of the drywall is installed – we are waiting for acoustic tiles and flooring for the gym area
  • change rooms and washrooms are substantially completed with plumping installs and tiling completed
  • waiting for doors, partitions and screening and work is also required to complete all of the HVAC and hydronic heating
  • exterior block work and glazing is substantially complete, all roofing completed

Fitness core:

  • The fitness core is nearing completion
  • all mechanical and electrical infrastructure is now complete
  • all the walls are in and painted
  • the flooring is going down, screening, doors and millwork and fixtures will be installed over the next two weeks
  • the tile work is substantially completed
  • the ceiling grid has been installed

Throughout the construction process, we will update you on parking, programming and other changes. Bookmark this page or check Facebook and Twitter for ongoing updates.

We will also post updates through other communication channels, such as e-newsletters.

Impacts to local residents

  • with ongoing excavation work, residents can expect a higher number of construction vehicles entering and exiting the site daily
  • the west entrance to the facility is temporarily closed for site servicing
  • residents may experience dust and loud noise
  • construction work will take place Monday through Friday between 7:00 a.m. and 5:00 p.m.
  • work may be required outside of these hours - if so, adherence to the noise bylaw will occur, or a variance notice will be given

Construction timelines

The WMRC expansion project has a 24 month construction schedule. Throughout the 24 months, the community will continue to see construction activities as well as construction equipment in and around the site. 

Completion dates:

  • occupancy of Community Pavilion: Summer 2021
  • total completion of project: Summer 2022